    1、You are about to take over a project from another project manager and find out the following information about the project. Activity Z has an early start (ES) of day 15 and a late start (LS) of day 20. Activity Z is a difficult activity.

     

    Cost performance index (CPI) is l.1.Schedule performance index (SPI) is 0.8.There are 11 stakeholders on the project. Based on this information, which of the following would you be the MOST concerned about?

     

    A.Schedule

     

    B.Float

     

    C.Cost

     

    D.The number of available resources

     

    你要从另一名项目经理手中接管一个项目,你发现了关于该项目的如下信息:活动Z的最早开始日期为15号,最晚开始日期为20号。活动Z很困难,其成本绩效指数(CPI)为1.1,进度计划执行指数(SPI)为0.8。该项目共有11名相关

     

    方。根据如上信息,你最关注的问题是:

     

    A.进度

     

    B.浮动时间

     

    C.成本

     

    D.可用资源数量

    长春PMP培训机构在线模拟题1

    2、After the project work is completed, a meeting is held with the client to deliver the four products. The client accepts two of the four products, and indicates that the remaining two projects don not meet the requirements. Before

     

    delivering the project, which process should the project manager have follow up to keep alignment with the customer's expectations?

     

    A. Control Quality

     

    B. Perform Quality Assurance

     

    C. Perform Quality Control Measurement

     

    D. Perform Quality Audit

     

    在项目工作完成后,与客户一起召开会议交付四个项目成果。客户接受四个成果中的两个,并表明剩余两个产品不满足需求。交付产品之前,项目经理应该遵循那个流程来确保与客户端期望保持一致?

     

    A.控制质量

     

    B.执行质量保证

     

    C.执行质量控制测量

     

    D.执行质量审计

    长春PMP培训机构在线模拟题2

     

    3、You are working on a research and development project in the agriculture industry. Your risk management team has identified several risks and has determined that the most significant risk to the project is a financial risk. The

     

    most effective response for this type of risk is:

     

    A. Avoidance

     

    B. Acceptance

     

    C. Mitigation

     

    D. Transference

     

    你参加一个农业的研发项目,风险管理团队识别了几个风险并认为项目最主要的风险是财务风险,此类风险最有效的应对方式是:

     

    A.规避

     

    B.接受

     

    C.减轻

     

    D.转移

    长春PMP培训机构在线模拟题2

     

    热门推荐

    分享到 更多
  • PMI®, PMP®, PMI-ACP® and PMBOK® are registered marks of the Project Management Institute, Inc.

    电话:025-84547600 / 13390908908 / 400-805-8908 / 传真:025-84547600 / 邮箱:welcome@smartpm.com.cn / Weixin:13327831928

    Copyright © 2009-2024 南京思摩特企业管理咨询有限公司 版权所有  苏ICP备11012816号-2   苏公网安备 32011402010832号

    技术支持:软月互动  

  • 咨询反馈
    扫码关注

    PMP、ACP项目管理培训顾问

    思摩特公众号

    返回顶部