欢迎大家来到思摩特海口PMP培训班,今天总结了我们部分学员的一些易错PMP考试试题给大家分享下:
1. Mark is in the middle of a software development project. So far, the project has incurred a total cost of $50,000. If it is determined the project is no longer required, what would we call the cost incurred to date?
A. Opportunity cost
B. Return on investment
C. Breakeven cost
D. Sunk cost
1. 马克正处于一个软件开发项目的中间。到目前为止,这个项目总共花费了50000美元。如果确定不再需要这个项目,我们会把已发生的成本叫做什么?
A. 机会成本
B. 投资回报率
C. 收支平衡成本
D. 沉没成本
2. Upon obtaining the project charter, the Project Manager of a project starts acquiring the project team immediately. Is this correct?
A. Yes. Acquisition of the project team is primarily an Initiating Process Group activity.
B. Yes. The project manager needs to get the team together as soon as the project starts.
C. No. It is the responsibility of the project sponsor to provide the team for execution.
D. No. Acquisition of the project team is primarily an Executing Process Group activity.
2. 项目经理在获得项目章程后,立即开始获取项目团队。这是正确的吗?
A. 正确。获取项目团队主要是启动过程组的活动
B. 正确。项目经理需要在项目一开始就获得项目团队
C. 错误。提供执行项目的团队是项目发起人的责任
D. 错误。获取团队主要是执行过程组的活动
3. An organization’s value chain can be represented by a special type of flowchart called SIPOC. SIPOC stands for:
A. Superior service, inferior service, peak hour service, optimized service, and client service
B. Simple, intellectual, procedural, optimal coding
C. Sample, information, practice, organization, and control
D. Suppliers, inputs, process, outputs, and customers
3. 组织的价值链可以用一种称作SIPOC的特殊流程图来表示,那么SIPOC代表:( )。
A. 优质服务,低效服务,高峰时间服务,优化服务,客户服务
B. 简单、智能、程序、最优编码
C. 样本、信息、实践、组织、控制
D. 供应商、输入、过程、输出、客户