欢迎大家来到思摩特北京PMP培训机构,今天总结了我们部分学员的一些易错PMP考试试题给大家分享下:
1. A project manager scheduled a review at the end of a phase, with the objective of obtaining authorization to close the current project phase and initiate the next phase. Which of the following is an incorrect way of describing this review?
A. Phase gate
B. Phase planning
C. Kill point
D. Stage gate
1. 项目经理计划了一次阶段末评审,目的是关闭当前的项目阶段和启动下一个阶段。关于此次评审,以下哪一项描述是错误的?
A. 阶段关口(phase gate)
B. 阶段规划
C. 关键决策点(kill point)
D. 阶段门(stage gate)
2. Which of the following tools and techniques is useful to process work performance data to identify sources of project defects during the Control Quality process?
A. Data analysis
B. Salience model
C. Schedule model
D. Communication model
2. 在质量控制过程,以下哪一个工具和技术用于处理工作绩效数据和识别项目缺陷()?
A. 数据分析
B. 凸显模型
C. 进度模型
D. 沟通模型
3. The Requirements Traceability Matrix helps in tracing all the following except:
A. Requirements to project objectives
B. Requirements to project scope
C. Requirements to test strategy
D. Requirements to project risk
3. 需求跟踪矩阵有助于跟踪以下所有,除了( )。
A. 需求到项目目标
B. 需求到项目范围
C. 需求到测试策略
D. 需求到项目风险